UK West Coast Route Modernisation Project
This example was created as a SE example directly for the SEBoK. It describes the United Kingdom West Coast Main Line railway project and some of the problems which occurred on this project before the implementation of SE. It also discussed the value of applying some aspects of SE, even if this is done later in the project.
この例は、SEBoK 向けに SE の例として直接作成されたものである。英国の西海岸本線鉄道プロジェクトと、SE の導入前にこのプロジェクトで生じた問題のいくつかを記述している。また、たとえプロジェクトの後の段階になってからであっても、SE のいくつかの側面を適用する価値についても論じている。
This example is based on information from a report by the UK National Audit Office (NAO 2006). It also uses an INCOSE publication on systems engineering case studies (INCOSE 2011) to help structure its conclusions.
この例は、英国会計検査院(UK National Audit Office)の報告書(NAO 2006)の情報に基づいている。また、結論を組み立てる助けとして、システムズエンジニアリングのケーススタディに関する国際システムズエンジニアリング協議会(INCOSE)の出版物(INCOSE 2011)も用いている。
The West Coast Main Line (WCML) is a principal United Kingdom (UK) railway artery serving London, the Midlands, the North West and Scotland. The Line is responsible for over 2,000 train movements each day, with more than 75 million rail journeys made each year on the route. It accounts for 43% of Britain’s UK freight market (Railway People 2011). In 1998, the British government embarked on a modernization program called the West Coast Route Modernisation (WCRM) project, to carry out a significant volume of modernization work between 1998 and 2008, delivering increased capacity and reduced journey times as well as replacing worn-out parts of the railway. It was a challenging job involving 640 kilometers of track—much of which was incapable of carrying high-speed rail cars. Some sections were seriously dilapidated, and new trains would require a complete overhaul of signaling, power supply, and switching systems.
Early on, the WCRM upgrade had serious problems. A major complicating factor was the introduction of a new signaling technology that was designed to allow improved services for new trains running at 140 miles per hour. By 2001, neither the rail infrastructure upgrade nor the new trains were on course for delivery as expected in the 1998 agreement. By May 2002, the projection of the program’s final cost had risen from £2.5 billion (in 1998) to £14.5 billion but had delivered only a sixth of the original scope.
In January 2002, the UK Secretary of State instructed the Strategic Rail Authority (SRA) to intervene and find a way to renew and upgrade the WCML. An SRA analysis identified the following issues: *The program lacked direction and leadership before 2002. *The project did not have a delivery strategy and there was no central point for responsibility and communication. *There was a lack of openness and communication regarding the program with interested parties before 2002 and there was a lack of stakeholder management. *Scope changes arose because WCRM did not have an agreed-upon specification that matched required outputs with inputs. *There was inadequate knowledge about the West Coast asset condition. *Technology issues related to the decision to replace conventional signaling with unproven moving block signaling introduced major risk into deliverability and cost before 2002. These technology issues caused scope changes and program delay. *Project management (PM) was weak, with a lack of senior management skills, too many changes in personnel, and ill-defined and fragmented roles and responsibilities. There was no integrated delivery plan and there was limited oversight of contractors. Poor management of contracts added to costs.
In order to remedy the situation, the SRA initiated the following actions, which align with generally accepted systems engineering (SE) practice: *A clear direction for the project was developed and documented in the June 2003 West Coast Main Line Strategy, specifying desired goals and outcomes. *A clear, measurable set of program outputs was established, along with more detailed infrastructure requirements, which were then subject to systematic change control and monitoring procedures fixing scope. Contractors were invited to tender complete detailed designs and deliver the work to a fixed price. *Clear program governance structures were instituted. *The SRA consulted widely with stakeholders and, in turn, kept stakeholders informed.
A National Audit Office (NAO) report concluded that the new arrangements worked well and that there were benefits to this approach (NAO 2006). Until this time, one of the program's key constraints and cost drivers had been the ability to access certain areas of the track. The new approach facilitated the ability to obtain possession of the track for engineering work, which was crucial to delivery. The new approach also enabled the program to identify opportunities to reduce the total cost by over £4 billion.
The NAO report also discussed a business case analysis by the SRA that identified the following benefits (NAO 2006): *benefit:cost ratio for the enhancements element was 2.5:1; *journey times and train frequencies exceeded the targets set out in the 2003 West Coast Strategy; *growth in passenger numbers exceeded expectations (e.g., by 2005-06, following Phase 1 of the West Coast program, annual passenger journeys on Virgin West Coast grew by more than 20%); and *punctuality improved (e.g., by September 2006, average time delays on Virgin West Coast trains have been approximately 9.5 minutes, a 43% improvement on the average delay of 17 minutes in September 2004).
The WCRM problems could be associated with a number of systems engineering concepts and practices: stakeholder needs definition, planning, analysis of risks and challenges of new technology and associated risk management, decision management, configuration or change management, information management, and management oversight.
西海岸本線(West Coast Main Line, WCML)は、ロンドン、ミッドランズ、北西部、スコットランドにサービスを提供する英国(United Kingdom, UK)の主要な鉄道幹線である。この路線は毎日2,000本を超える列車の運行を担っており、このルートでは毎年7,500万回を超える鉄道での移動が行われている。また、英国の貨物市場の43%を占めている(Railway People 2011)。1998年、英国政府は西海岸ルート近代化(West Coast Route Modernisation, WCRM)プロジェクトと呼ばれる近代化プログラムに着手した。これは、1998年から2008年にかけて相当量の近代化工事を実施し、輸送力の増強と所要時間の短縮を実現するとともに、鉄道の老朽化した部分を置き換えるものであった。640キロメートルに及ぶ軌道を対象とする困難な事業であり、その軌道の多くは高速鉄道車両の走行に対応できなかった。一部の区間は深刻に荒廃しており、新しい列車を走らせるには信号、電力供給、転轍システムを全面的に改修する必要があった。
初期の段階で、WCRM のアップグレードには深刻な問題があった。大きな複雑化要因となったのは、時速140マイルで走行する新しい列車のサービス向上を可能にするよう設計された、新しい信号技術の導入であった。2001年までに、鉄道インフラのアップグレードも新しい列車も、1998年の合意で予期されたとおりの納入に向かって進んではいなかった。2002年5月までに、プログラムの最終コストの見通しは(1998年の)£2.5 billion から £14.5 billion へと膨らんだが、納入されたのは当初のスコープの6分の1にすぎなかった。
2002年1月、英国国務大臣は戦略鉄道庁(Strategic Rail Authority, SRA)に対し、介入して WCML を更新・アップグレードする方策を見出すよう指示した。SRA の分析により、以下の問題が特定された:
この状況を是正するため、SRA は以下の行動を開始した。これらは、一般に受け入れられているシステムズエンジニアリング(systems engineering)(SE)の実践に合致するものである:
会計検査院(National Audit Office, NAO)の報告書は、新しい体制がうまく機能し、このアプローチには便益があったと結論づけた(NAO 2006)。それまで、プログラムの主要な制約およびコストドライバの1つは、軌道の特定の区域に立ち入ることができるかどうかであった。新しいアプローチにより、工事のために軌道を占有する許可が得やすくなり、これは納入にとって決定的に重要であった。また、新しいアプローチによって、プログラムは総コストを £4 billion を超えて削減する機会を特定できるようになった。
NAO の報告書はまた、SRA によるビジネスケース分析についても論じており、この分析では以下の便益が特定された(NAO 2006):
WCRM の問題は、システムズエンジニアリングの多くの概念や実践と関連づけることができる。すなわち、ステークホルダーニーズ定義、計画、リスクおよび新技術の課題の分析とそれに関連するリスクマネジメント、決定マネジメント、構成管理または変更管理、情報マネジメント、そしてマネジメントによる監督である。
The WCRM project illustrates that when SE concepts and practices are not used or applied properly, system development can experience debilitating problems. This project also demonstrates how such problems can be abated and reversed when SE principles and methods are applied.
WCRM プロジェクトは、SE の概念と実践が用いられない、あるいは適切に適用されない場合に、システム開発が深刻な打撃となる問題に直面し得ることを例示している。また、このプロジェクトは、SE の原則と方法を適用すれば、そうした問題をどのように軽減し、好転させ得るかも示している。
INCOSE Transportation Working Group. Systems Engineering in Transportation Projects: A Library of Case Studies, version 1.0. Seattle, WA, USA: International Council on Systems Engineering. March 9th, 2011.
NAO. The Modernisation of the West Coast Main Line, Report by the Comptroller and Auditor General. London, UK: National Audit Office. November 22, 2006. HC 22 Session 2006-2007.
Railway People. '"West Coast Route Modernisation." RailwayPeople. 2011. Accessed July 25, 2011. Available at: https://www.railwaypeople.com/rail-projects/west-coast-route-modernisation-3.html.
None.
None.