Hubble Space Telescope
This article describes a remarkable engineering feat with vast scientific benefits and implications. The topic may be of particular interest to those facing formidable challenges where one might thrive on a thoughtful blend of humility and optimism. For additional information, refer to the links provided in Section V: Lessons Learned below.
本記事では、広大な科学的利益と含意を持つ驚くべき工学的偉業を取り上げる。謙虚さと楽観主義を思慮深く組み合わせることで成功を収め得るような、困難なシステムズエンジニアリング(Systems Engineering)の課題に直面している人々にとって、このトピックは特に興味深いものであろう。詳しくは、後述の第V節「教訓」に示したリンクを参照されたい。
The Hubble Space Telescope (HST) Case Study was developed by the United States Air Force Center for Systems Engineering (AF CSE) located at the Air Force Institute of Technology (AFIT). The AF CSE was tasked to develop case studies focusing on the application of principle (glossary) s within various aerospace framework (glossary) (Friedman and Sage 2003; Friedman and Sage 2004, 84-96), which decomposes a case into contractor, government, and shared responsibilities in the following nine concept areas: STOPPED HERE #Requirements Definition and Management #Systems Architecture Development #System/Subsystem Design #Verification/Validation #Risk Management #Systems Integration and Interfaces #Life Cycle Support #Deployment and Post Deployment #System and Program Management
The case study provides a useful example of the rising design (glossary) stage, or detected and fixed with a $10 million investment in an end-to-end test of the telescope on the ground, ended up costing $1 billion to fix when the system was in .
The Hubble Space Telescope (HST) Case Studyは、Air Force Institute of Technology(AFIT)に置かれたUnited States Air Force Center for Systems Engineering(AF CSE)が作成したものである。AF CSEは、さまざまな航空宇宙プログラム(program)におけるシステムズエンジニアリング(Systems Engineering)の原則(principle)の適用に焦点を当てたケーススタディを作成する任務を負っていた。HSTの研究(Mattice 2005)は、システムズエンジニアリングの大学院教育を支援する目的でAFITが作成対象に選んだ、最初の4つのケーススタディの一つである。これらのケースはFriedman-Sageフレームワーク(framework)(Friedman and Sage 2003; Friedman and Sage 2004, 84-96)に沿って構成されている。このフレームワークは、ケースを次の9つの概念領域ごとに、請負者の責任、政府の責任、両者が共有する責任へと分解するものである。
STOPPED HERE
このケーススタディは、ライフサイクルフェーズが進むにつれて欠陥修正のコスト(cost)が増大していくことを示す有用な例である。(試験フィクスチャの仕様における)ある誤りは、設計(design)段階であれば$1,000で修正でき、あるいは地上で望遠鏡のエンドツーエンド試験に$10 millionを投じることによって検出・修正することもできた。しかし実際には、システムが運用(service)に入ってから修正することになり、その費用は$1 billionに達した。
The Hubble Space Telescope (HST) is an orbiting astronomical observatory operating in the spectrum from the near-infrared into the ultraviolet. Launched in 1990 and still operational, HST carries and has carried a wide variety of instruments producing imaging, spectrographic, astrometric, and photometric data through both pointed and parallel observing programs. Over 100,000 observations of more than 20,000 targets have been produced for retrieval. The telescope is well known as a marvel of science. This case study hopes to represent the facet of the HST that is a marvel of systems engineering, which, in fact, generated the scientific research and observation capabilities now appreciated worldwide.
ハッブル宇宙望遠鏡(Hubble Space Telescope、HST)は、近赤外から紫外までのスペクトル域で観測を行う軌道上の天文台である。1990年に打ち上げられて現在も運用が続いており、HSTはこれまで、指向観測プログラムと並行観測プログラムの双方を通じて撮像、分光、天文測定、測光のデータを生み出す多種多様な機器を搭載してきたし、現在も搭載している。20,000を超える観測対象について、100,000回を超える観測のデータが取得可能になっている。この望遠鏡が科学の驚異であることはよく知られている。本ケーススタディが描き出そうとするのは、HSTの、システムズエンジニアリングの驚異としての側面である。実のところ、今日世界中で高く評価されている科学研究と観測の能力を生み出したのは、まさにこの側面なのである。
Viewed with the clarity that only time and hindsight provide, the HST program certainly represents one of the most successful modern human endeavors on any scale of international scope and requirement (glossary) s from the diverse international scientific community at a time when NASA was implementing a different research-development-acquisition philosophy and Systems Engineer (glossary) s in effect had to acknowledge as integral to their overall system/program/engineering management responsibility.
時間と後知恵によってはじめて得られる明晰さをもって振り返れば、HSTプログラムは、国際的な規模と複雑さのいかなる尺度で見ても、現代の人類が成し遂げた最も成功した取り組みの一つであることは確かである。システムズエンジニアリングプロジェクトとして、HSTは多様な国際科学コミュニティから提示された要求事項(requirement)に応えなければならなかった。しかも当時のNASAは、主要な政府取得プログラムの大部分で主に用いられていたものとは異なる研究・開発・取得の理念とプロセス(process)を実施していた。他の大部分の大規模プログラムと同様に、システムズエンジニアリングプロセスそのものの外部にある強力な影響が問題となり、HSTのシステムズエンジニア(Systems Engineer)は、事実上、それらを自らのシステム/プログラム/エンジニアリング管理責任全体に不可欠な一部として受け止めなければならなかった。
The story of how this remarkable capability came to be is a story of the complicated interactions of a systems engineering process, which we like to believe we understand, with equally demanding political, budgetary, and institutional processes we often fail to understand or comprehend at the time they occur. In the final analysis, these processes are inseparable and integral to attaining program success. The challenge to modern systems engineers is to fully embrace the discipline of the systems engineering process while at the same time learning how to continue to practice it in spite of inevitable external influences and instabilities that often cannot be anticipated.
この驚くべき能力がいかにして生まれたかという物語は、我々が理解していると信じていたいシステムズエンジニアリングプロセスと、同じく厳しい要求を伴いながら、その渦中にあってはしばしば理解も把握もできない政治的、予算的、制度的プロセスとが、複雑に相互作用する物語である。結局のところ、これらのプロセスは切り離すことができず、プログラムを成功に導くうえで不可欠である。現代のシステムズエンジニアに課せられた課題は、システムズエンジニアリングプロセスの規律を全面的に受け入れながら、避けられず、しかもしばしば予測できない外部からの影響や不安定さがあっても、その実践を続ける方法を身につけることである。
Major differences revolved around the nature and needs of a very different HST “customer” or user from most DoD systems. The HST had to respond to requirements from the diverse international scientific community instead of from DoD’s combatant commands. In addition, at the time, NASA implemented a different research-development-acquisition philosophy and process than the DoD Acquisition Management Framework described in the DoD 5000 series acquisition reforms. As with most other large programs, powerful influences outside the systems engineering process itself became issues that HST systems engineers in effect had to acknowledge as integral to their overall system/program/engineering management responsibility.
主な違いは、大部分のDoDシステムとは大きく異なるHSTの「顧客」すなわちユーザの性質とニーズをめぐるものであった。HSTは、米国防総省の戦闘軍(combatant commands)のためではなく、多様な国際科学コミュニティから提示された要求事項に応えなければならなかった。さらに当時のNASAは、DoD 5000シリーズの取得改革に記述されたDoD Acquisition Management Frameworkとは異なる研究・開発・取得の理念とプロセスを実施していた。他の大部分の大規模プログラムと同様に、システムズエンジニアリングプロセスそのものの外部にある強力な影響が問題となり、HSTのシステムズエンジニアは、事実上、それらを自らのシステム/プログラム/エンジニアリング管理責任全体に不可欠な一部として受け止めなければならなかった。
During the critical systems engineering phase for the HST program (1970s concept studies thru 1990 launch) there appears to have been no NASA systems engineering master process. Rather, field center processes were operative and possibly even in competition, as centers (especially Marshall and Goddard for HST) were in keen competition for lead management roles and responsibilities. We will see the systems engineering and program management impacts of this competition as it played out for HST, with the science mission objectives and instrumentation payloads being the motivation for Goddard vs. the vehicle/payload access to space motivation of Marshall. In the final analysis, the roles of the major contractors in engineering the system with uneven NASA participation over the system life cycle had a telling effect.
HSTプログラムにとって重要なシステムズエンジニアリングの段階(1970年代の概念検討から1990年の打ち上げまで)には、NASAとしてのシステムズエンジニアリングのマスタープロセスは存在しなかったようである。代わりに各フィールドセンターのプロセスが機能しており、それらは互いに競合してさえいた可能性がある。各センター(HSTについては特にMarshallとGoddard)が、主導的な管理の役割と責任をめぐって激しく競い合っていたからである。この競合がHSTにおいてどのように展開し、システムズエンジニアリングとプログラム管理にどのような影響を及ぼしたかを、以下で見ていく。Goddardの動機は科学ミッションの目的と計測ペイロードにあり、一方Marshallの動機はビークル/ペイロードの宇宙へのアクセスにあった。結局のところ、システムのライフサイクルを通じてNASAの関与にむらがあるなかで、システムのエンジニアリングを担った主要請負者の役割が顕著な影響を及ぼしたのである。
Five learning principles (LPs) were derived that address the more broadly applicable areas of systems engineering knowledge. These five LPs inform the areas of the SEBoK that are most strongly related to the case study. The five areas are:
*stakeholder requirements definition (LP1); *planning (pre-program trade studies) (LP2); *system integration (LP3); *life cycle model management (LP4); and *risk management (LP5).
A synopsis of the HST Learning Principles (LPs) are as follows:
Stakeholder Requirements Definition LP1: Early and full participation by the customer/user throughout the program is essential to success. In the early stages of the HST program, the mechanism for involving the customer was not well defined. The user community was initially polarized and not effectively engaged in program definition and advocacy. This eventually changed for the better, albeit driven heavily by external political and related national program initiatives. Ultimately, institutionalization of the user’s process for involvement ensured powerful representation and a fundamental stake and role in both establishing and managing program requirements. Over time, the effectiveness of “The Institute” led to equally effective user involvement in the deployment and on-orbit operations of the system as well.
Planning LP 2: The use of Pre-Program Trade Studies (e.g. “Phased Studies” or “Phased Project Planning”) to broadly explore technical concepts and alternatives is essential and provides for a healthy variety of inputs from a variety of contractors and government (NASA) centers. These activities cover a range of feasibility, conceptual, alternative and preliminary design trades, with cost initially a minor (later a major) factor. In the case of HST, several NASA Headquarters and Center organizations funded these studies and sponsored technical workshops for HST concepts. This approach can promote healthy or unhealthy competition, especially when roles and responsibilities within and between the participating management centers have not yet been decided and competing external organizations use these studies to further both technical and political agendas. NASA Center roles and missions can also be at stake depending on political and or budgetary realities. The systems engineering challenge at this stage is to “keep it technical, stupid!”
Systems Integration LP 3: A high degree of systems integration to assemble, test, deploy, and operate the system is essential to success and must be identified as a fundamental program resource need as part of the program baseline. For HST, the early wedding of the program to the Shuttle, prior NASA and NASA contractor experience with similarly complex programs, such as Apollo, and the early requirement for manned, on-orbit servicing made it hard not to recognize this was a big systems engineering integration challenge. Nonetheless, collaboration between government engineers, contractor engineers, as well as customers, must be well defined and exercised early on to overcome inevitable integration challenges and unforeseen events.
Life Cycle Models LP 4: Life Cycle Support planning and execution must be integral from day one, including concept and design phases. The results will speak for themselves. Programs structured with real life cycle performance as a design driver will be capable of performing in-service better, and will be capable of dealing with unforeseen events (even usage in unanticipated missions). HST probably represents a benchmark for building in system sustainment (reliability, maintainability, provision for technology upgrade, built-in redundancy, etc.), while providing for human execution of functions (planned and unplanned) critical to servicing missions. With four successful service missions complete, including one initially not planned (the primary mirror repair), the benefits of design-for-sustainment, or life cycle support, throughout all phases of the program become quite evident. Without this design approach, it is unlikely that the unanticipated, unplanned mirror repair could even have been attempted, let alone been totally successful.
Risk Management LP 5: For complex programs, the number of stakeholders (government and contractor) demands that the program be structured to cope with high risk factors in many management and technical areas simultaneously. The HST program relied heavily on the contractors (especially Lockheed Missiles and Space Company (LMSC) and Perkin-Elmer (P-E)), each of which “owned” very significant and unique program risk areas. In the critical area of optical systems, NASA depended on LMSC as the overall integrator to manage risk in an area where P-E was clearly the technical expert. Accordingly, NASA relied on LMSC and LMSC relied on P-E with insufficient checks, oversight, and independence of the quality assurance function throughout. While most other risk areas were no doubt managed effectively, lapses here led directly to the HST’s going to orbit with the primary mirror defect undetected, in spite of substantial evidence that could have been used to prevent this.
より広く適用できるシステムズエンジニアリング知識の領域を扱う、5つの学習原則(Learning Principles、LP)が導き出された。これら5つのLPは、本ケーススタディと最も関係の深いSEBoKの領域に知見を与える。5つの領域は次のとおりである。
HSTの学習原則(LP)の概要は次のとおりである。
ステークホルダー要求定義 LP1:プログラム全体を通じて顧客/ユーザが早期から全面的に参加することが、成功に不可欠である。HSTプログラムの初期段階では、顧客を関与させる仕組みが十分に定められていなかった。ユーザコミュニティは当初、意見が二極化しており、プログラムの定義や支持を求める活動に効果的に関わっていなかった。この状況は最終的に好転したが、それは外部の政治的および関連する国家プログラムのイニシアチブによって強く駆動されたものであった。最終的には、ユーザが関与するためのプロセスが制度化されたことで、ユーザの意見を強く代表できる体制が整い、プログラム要求事項の確立と管理の両方に主要な当事者として関与できるようになった。やがて「The Institute」が有効に機能したことで、システムの展開や軌道上運用においても、同様に効果的なユーザの関与が実現した。
計画 LP 2:技術的な概念や代替案を幅広く探るために、プログラム前のトレードスタディ(例えば「Phased Studies」や「Phased Project Planning」)を用いることは不可欠であり、それによってさまざまな請負者や政府(NASA)のセンターから健全な多様性を持つインプットが得られる。これらのアクティビティは、実現可能性、概念、代替案、予備設計といった一連のトレードを対象とし、コストは当初は副次的な(後に主要な)要因となる。HSTの場合、NASA本部とセンターのいくつかの組織がこれらの検討に資金を提供し、HSTの概念に関する技術ワークショップを主催した。このアプローチは、健全な競争を促すこともあれば、不健全な競争を促すこともある。特に、参加する管理センター内およびセンター間の役割と責任がまだ決まっておらず、競合する外部組織がこれらの検討を技術的および政治的なアジェンダの双方を推進するために利用する場合はそうである。政治的または予算的な現実によっては、NASAセンターの役割やミッションそのものが懸かることもある。この段階におけるシステムズエンジニアリングの課題は、「技術に徹すること(keep it technical, stupid!)」である。
システム統合 LP 3:システムを組み立て、試験し、展開し、運用するための高度なシステム統合は成功に不可欠であり、プログラムベースラインの一部として、プログラムの基本的な資源ニーズに位置づけなければならない。HSTの場合、プログラムが早い時期からシャトルと結びついていたこと、NASAとNASAの請負者がApolloのような同様に複雑なプログラムを経験していたこと、そして軌道上での有人整備が早期から要求されていたことから、これがシステムズエンジニアリングにおける大きな統合の課題であることは、認識しないほうが難しかった。それでもなお、避けられない統合の課題や予見できない出来事を乗り越えるには、政府のエンジニア、請負者のエンジニア、そして顧客の間の協働を早期から明確に定め、実践しなければならない。
ライフサイクルモデル LP 4:ライフサイクル支援の計画と実行は、概念フェーズや設計フェーズを含め、初日から不可欠な要素として組み込まれていなければならない。その成果はおのずと明らかになる。実際のライフサイクル性能を設計ドライバとして構成されたプログラムは、運用中により高い性能を発揮でき、予見できない出来事(想定外のミッションでの使用でさえ)にも対処できる。HSTはおそらく、システムの維持(信頼性、保全性、技術アップグレードへの備え、組み込みの冗長性など)を設計に織り込みつつ、整備ミッションにとって重要な機能を(計画されたものも計画外のものも)人間が実行できるようにした点で、ベンチマークとなる存在である。当初は計画されていなかった1回(主鏡の修理)を含め、4回の整備ミッションが成功裏に完了したことで、プログラムの全フェーズを通じたシステムの維持を見据えた設計、すなわちライフサイクル支援の利点は極めて明白になっている。この設計アプローチがなければ、予期せず計画もされていなかった主鏡の修理は、完全な成功はおろか、試みることさえできなかった可能性が高い。
リスク管理 LP 5:複雑なプログラムでは、ステークホルダー(政府と請負者)の数が多いため、多くの管理領域と技術領域にわたる高いリスク要因に同時に対処できるようにプログラムを構成する必要がある。HSTプログラムは請負者(特にLockheed Missiles and Space Company(LMSC)とPerkin-Elmer(P-E))に大きく依存しており、各社が極めて重要かつ固有のプログラムリスク領域の管理責任を負っていた。光学システムという重要な領域において、NASAは、P-Eが明らかに技術的専門家である領域のリスク管理について、全体統合者としてのLMSCに頼っていた。つまり、NASAはLMSCに依存し、LMSCはP-Eに依存していたが、全過程を通じてチェックと監督が不十分で、品質保証機能の独立性も不足していた。他のリスク領域の大半は間違いなく効果的に管理されていたものの、ここでの失策は、それを防ぐために用いることができたであろう相当な証拠があったにもかかわらず、主鏡の欠陥が検出されないままHSTが軌道に投入されることに直接つながった。
Friedman, G.R. and A.P. Sage. 2003. Systems Engineering Concepts: Illustration Through Case Studies. Accessed September 2011. Available at: https://www.afit.edu/cse/docs/Friedman-Sage%20Framework.pdf.
Friedman, G. and A. Sage. 2004. “Case Studies of Systems Engineering and Management in Systems Acquisition.” Systems Engineering. 7(1): 84-96.
Mattice, J. “Hubble Space Telescope Case Study." Ft. Belvoir, VA: Defense Acquisition University (DAU). Last modified May 2, 2005. Accessed November 27, 2012. Available at https://acc.dau.mil/adl/en-US/37600/file/9105/Hubble%20Space%20Telescope%20SE%20Case%20Study%20-%20JJ%20Mattice.pdf.