プロジェクト評価と管理

Project Assessment and Control

表示:

The purpose of systems engineering assessment and control (SEAC) is to provide adequate visibility into the project’s actual technical progress and risks with respect to the technical plans (i.e., systems engineering management plan (SEMP) or systems engineering plan (SEP) and subordinate plans). The visibility allows the project team to take timely preventive action when disruptive trends are recognized or corrective action when performance deviates beyond established thresholds or expected values. SEAC includes preparing for and conducting reviews and audits to monitor performance. The results of the reviews and measurement analyses are used to identify and record findings/discrepancies and may lead to causal analysis and corrective/preventive action plans. Action plans are implemented, tracked, and monitored to closure. (NASA 2007, Section 6.7; SEG-ITS, 2009, Section 3.9.3, 3.9.10; INCOSE, 2010, Clause 6.2; SEI, 2007)

システムズエンジニアリング評価・管理(systems engineering assessment and control、SEAC)の目的は、技術計画(すなわち、システムズエンジニアリングマネジメント計画(systems engineering management plan、SEMP)またはシステムズエンジニアリング計画(systems engineering plan、SEP)、および下位計画)に照らして、プロジェクト(project)の実際の技術的進捗とリスク(risks)を十分に可視化することである。この可視化により、プロジェクトチームは、混乱を招く傾向が認識されたときには適時に予防処置を講じ、性能が設定された閾値または期待値を超えて逸脱したときには是正処置を講じることができる。SEAC には、性能を監視するためのレビューと監査の準備および実施が含まれる。レビューと測定(measurement)分析の結果は、所見/不整合を特定し記録するために用いられ、原因分析と是正/予防処置計画につながることがある。処置計画は実施・追跡され、完了まで監視される(NASA 2007, Section 6.7; SEG-ITS, 2009, Section 3.9.3, 3.9.10; INCOSE, 2010, Clause 6.2; SEI, 2007)。

Systems Engineering Assessment and Control Process Overview

システムズエンジニアリング評価・管理プロセスの概要

The SEAC process involves determining and initiating the appropriate handling strategies and actions for findings and/or discrepancies that are uncovered in the enterprise, infrastructure, or life cycle activities associated with the project. Analysis of the causes of the findings/discrepancies aids in the determination of appropriate handling strategies. Implementation of approved preventive, corrective, or improvement actions ensures satisfactory completion of the project within planned technical, schedule, and cost objectives. Potential action plans for findings and/or discrepancies are reviewed in the context of the overall set of actions and priorities in order to optimize the benefits to the project and/or organization. Interrelated items are analyzed together to obtain a consistent and cost-effective resolution.

The SEAC process includes the following steps:

The following activities are normally conducted as part of a project assessment and control process:

Examples of major technical reviews used in SEAC are shown in Table 1 from DAU (2010).

SEAC プロセスには、プロジェクトに関連するエンタープライズ、インフラストラクチャ、またはライフサイクルのアクティビティにおいて発見された所見および/または不整合に対して、適切な対処戦略と処置を決定し、着手することが含まれる。所見/不整合の原因を分析することは、適切な対処戦略を決定するうえで役立つ。承認された予防処置、是正処置、または改善処置を実施することにより、計画された技術、スケジュール、およびコストの目標の範囲内で、プロジェクトが満足に完了することが確実になる。所見および/または不整合に対する処置計画の候補は、プロジェクトおよび/または組織にとっての便益を最適化するために、処置と優先順位の全体に照らしてレビューされる。相互に関連する項目は、一貫性があり費用対効果の高い解決を得るために、まとめて分析される。

SEAC プロセスには、以下のステップが含まれる。

以下のアクティビティは、通常、プロジェクト評価・管理プロセスの一部として実施される。

SEAC で用いられる主要な技術レビューの例を、DAU(2010)による表1に示す。

表1. 主要な技術レビューの例(DAU 2012)。Defense Acquisition University(DAU)/U.S. Department of Defense(DoD)により公表。

+ Table 1. Major Technical Review Examples (DAU 2012). Released by Defense Acquisition University (DAU)/U.S. Department of Defense (DoD).
Name
Description
Alternative Systems Review
Critical Design Review (CDR)
Functional Configuration Audit
In-Service Review
Initial Technical Review
Integrated Baseline Review
Operational Test Readiness Review
Production Readiness Review (PRR)
Physical Configuration Audit
Preliminary Design Review (PDR)
System Functional Review (SFR)
System Requirements Review (SRR)
System Verification Review (SVR)
Technology Readiness Assessment
Test Readiness Review (TRR)
名前説明
代替システムレビュー結果として得られる要求事項の集合が顧客のニーズと期待に合致していることを確実にするための、複数分野によるレビュー。
重要設計レビュー(Critical Design Review、CDR)レビュー対象のシステムが、現在割り当てられている予算とスケジュールの範囲内で能力開発文書の要求事項を満たす合理的な見込みがあることを確実にし、初期製品ベースラインを確立するための、複数分野によるレビュー。
機能構成監査機能ベースラインにおける設計要求事項およびインターフェース要求に実際の性能が準拠していることを検証する目的で、構成(configuration)品目(ハードウェアとソフトウェア)の試験時に確認された構成品目(ハードウェアとソフトウェア)の特性を正式に検査すること。
運用中レビューレビュー対象のシステムが、十分に理解され管理されたリスクのもとで運用に供されていることを確実にするために実施される、複数分野による製品およびプロセスの評価。
初期技術レビュープログラムによる初期プログラム目標覚書の提出を支援する、複数分野によるレビュー。
統合ベースラインレビュー性能測定ベースラインを確立するために、政府のプログラムマネージャーと請負業者が共同で実施する評価。
運用テスト準備レビューシステムが高い成功確率で初期運用テスト・評価に進めること、また、実運用で有効に機能し、実運用への導入に適しているであることを確実にするための、複数分野による製品およびプロセスの評価。
生産準備レビュー(Production Readiness Review、PRR)設計が生産に移行できる状態にあるかどうか、ならびに、主請負業者と主要な下請業者が、スケジュール、性能、コスト、またはその他の確立された基準の閾値を破るような許容できないリスクを負うことなく、適切な生産計画を策定し終えているかどうかを判断するための、プログラムの検査。
物理構成監査全規模生産の決定が行われる頃に、生産中の品目の実際の構成(configuration)を検査すること。
基本設計審査(PDR)(Preliminary Design Review、PDR)レビュー対象のシステムが運用上効果的かつ適切であると判断される合理的な見込みがあることを確実にし、物理要素への割り当てを定めたベースラインを確立するための技術評価。
システム機能レビュー(System Functional Review、SFR)システムの機能ベースラインが確立されており、現在割り当てられている予算とスケジュールの範囲内で、初期能力文書または能力開発文書草案の要求事項を満たす合理的な見込みがあることを確実にするための、複数分野によるレビュー。
システム要求審査(System Requirements Review、SRR)レビュー対象のシステムが初期システム開発に進めること、ならびに、初期能力文書または能力開発文書草案から導出されたすべてのシステム要求事項と性能要求事項が定義済みかつテスト可能であり、コスト、スケジュール、リスク、技術成熟度、およびその他のシステム制約と整合していることを確実にするための、複数分野によるレビュー。
システム検証レビュー(System Verification Review、SVR)レビュー対象のシステムが、コスト(プログラム予算)、スケジュール(プログラムスケジュール)、リスク、およびその他のシステム制約の範囲内で、低率初期生産および全規模生産に進めることを確実にするための、複数分野による製品およびプロセスの評価。
技術成熟度評価維持整備を左右する要因などの基幹技術要素の成熟度を評価する、体系的で測定基準に基づくプロセス。
テスト準備レビュー(Test Readiness Review、TRR)レビュー対象のサブシステムまたはシステムが正式なテストに進む準備が整っていることを確実にするよう設計された、複数分野によるレビュー。

Linkages to Other Systems Engineering Management Topics

他のシステムズエンジニアリングマネジメントトピックとの連関

The SE assessment and control process is closely coupled with the measurement, planning, decision management, and risk management processes. The measurement process provides indicators for comparing actuals to plans. Planning provides estimates and milestones that constitute plans for monitoring as well as the project plan, which uses measurements to monitor progress. Decision management uses the results of project monitoring as decision criteria for making control decisions.

SE 評価・管理プロセスは、測定、計画立案、意思決定マネジメント、およびリスクマネジメントの各プロセスと密接に結びついている。測定プロセスは、実績を計画と比較するための指標を提供する。計画立案は、監視のための計画を構成する見積もりとマイルストーン、および、測定を用いて進捗を監視するプロジェクト計画を提供する。意思決定マネジメントは、プロジェクト監視の結果を、管理上の意思決定を行うための判断基準として用いる。

Practical Considerations

実務上の考慮事項

Key pitfalls and good practices related to SEAC are described in the next two sections.

SEAC に関連する主な落とし穴と優れた実践を、以下の2つの節で述べる。

Pitfalls

落とし穴

Some of the key pitfalls encountered in planning and performing SE assessment and control are shown in Table 2.

SE 評価・管理の計画立案と実施において遭遇する主な落とし穴の一部を、表2に示す。

表2. 評価と管理における主な落とし穴。(SEBoK Original)

+Table 2. Major Pitfalls with Assessment and Control. (SEBoK Original)
Name
Description
No Measurement
Since the assessment and control activities are highly dependent on insightful measurement information, it is usually ineffective to proceed independently from the measurement efforts - what you get is what you measure.
"Something in Time" Culture
Some things are easier to measure than others - for instance, delivery to cost and schedule. Don't focus on these and neglect harder things to measure like quality of the system. Avoid a "something in time" culture where meeting the schedule takes priority over everything else, but what is delivered is not fit for purpose, resulting in the need to rework the project.
No Teeth
Make sure that the technical review gates have "teeth". Sometimes the project manager is given authority (or can appeal to someone with authority) to over-ride a gate decision and allow work to proceed, even when the gate has exposed significant issues with the technical quality of the system or associated work products. This is a major risk if the organization is strongly schedule-driven; it can't afford the time to do it right, but somehow it finds the time to do it again (rework).
Too Early Baselining
Don't baseline requirements or designs too early. Often there is strong pressure to baseline system requirements and designs before they are fully understood or agreed, in order to start subsystem or component development. This just guarantees high levels of rework.
名前説明
測定なし評価と管理のアクティビティは、洞察に富む測定情報に大きく依存しているため、測定の取り組みと切り離して進めても、通常は効果が上がらない。得られるのは、測定したものである。
「Something in Time」文化ほかのものより測定しやすいものがある。たとえば、コストとスケジュールどおりの納入である。これらに集中するあまり、システムの品質のような測定の難しいものを軽視してはならない。スケジュールを守ることが他の何よりも優先される一方で、納入されるものが目的に適合せず、結果としてプロジェクトの手戻りが必要になるような「something in time」文化を避けること。
実効性なし技術レビューのゲートに「実効性(teeth)」を確実に持たせること。ゲートがシステムまたは関連する作業成果物の技術的品質について重大な課題を明らかにした場合でも、プロジェクトマネージャーに、ゲートの決定を覆して(あるいは権限を持つ者に訴えて)作業の続行を認める権限が与えられていることがある。組織が強くスケジュール主導である場合、これは大きなリスクとなる。正しく行う時間は確保できないのに、なぜかやり直す(手戻りする)時間は見つかるのである。
時期尚早なベースライン化要求事項や設計を早すぎる段階でベースライン化してはならない。サブシステムやコンポーネントの開発に着手するために、システム要求事項と設計が十分に理解され合意される前に、それらをベースライン化するよう強い圧力がかかることが多い。これは、大量の手戻りを確実に招くだけである。

Good Practices

優れた実践

Some good practices gathered from the references are shown in Table 3.

参考文献から集めた優れた実践の一部を、表3に示す。

表3. 評価と管理における実証済みの実践。(SEBoK Original)

+Table 3. Proven Practices with Assessment and Control. (SEBoK Original)
Name
Description
Independence
Provide independent (from customer) assessment and recommendations on resources, schedule, technical status, and risk based on experience and trend analysis.
Peer Reviews
Use peer reviews to ensure the quality of a product’s work before they are submitted for gate review.
Accept Uncertainty
Communicate uncertainties in requirements or designs and accept that uncertainty is a normal part of developing a system.
Risk Mitigation Plans
Do not penalize a project at gate review if they admit uncertainty in requirements - ask for their risk mitigation plan to manage the uncertainty.
Just In-Time Baselining
Baseline requirements and designs only when you need to - when other work is committed based on the stability of the requirement or design. If work must start and the requirement or design is still uncertain, consider how you can build robustness into the system to handle the uncertainty with minimum rework.
Communication
Document and communicate status findings and recommendations to stakeholders.
Full Visibility
Ensure that action items and action-item status, as well as other key status items, are visible to all project participants.
Leverage Previous Root Cause Analysis
When performing root cause analysis, take into account the root cause and resolution data documented in previous related findings/discrepancies.
Concurrent Management
Plan and perform assessment and control concurrently with the activities for Measurement and Risk Management.
Lessons Learned and Post-Mortems
Hold post-delivery assessments or post-project reviews to capture knowledge associated with the project – e.g., to augment and improve estimation models, lessons learned databases, gate review checklists, etc.
名前説明
独立性経験と傾向分析に基づき、資源、スケジュール、技術的状況、およびリスクについて、(顧客から)独立した評価と勧告を提供する。
ピアレビューピアレビューを用いて、製品に関する作業がゲートレビューに提出される前に、その品質を確実なものにする。
不確かさ(Uncertainty)を受け入れる要求事項や設計における不確かさを伝え、不確かさがシステム開発における通常の要素であることを受け入れる。
リスク軽減計画要求事項における不確かさを認めたからといって、ゲートレビューでプロジェクトを罰してはならない。その不確かさを管理するためのリスク軽減計画を彼らに求めること。
ジャストインタイムのベースライン化要求事項と設計は、必要になったとき、すなわち要求事項や設計の安定性を前提として他の作業が確約されるときにのみ、ベースライン化する。要求事項や設計がまだ不確かな状態で作業を開始しなければならない場合は、最小限の手戻りで不確かさに対処できるよう、システムにどのようにロバスト性を組み込めるかを検討する。
コミュニケーション状況に関する所見と勧告を文書化し、ステークホルダーに伝える。
完全な可視性処置項目とその状況、ならびにその他の主要な状況項目を、すべてのプロジェクト参加者が確実に確認できるようにする。
過去の根本原因分析を活用する根本原因分析を実施する際は、過去の関連する所見/不整合において文書化された根本原因と解決のデータを考慮に入れる。
並行マネジメント測定およびリスクマネジメントのアクティビティと並行して、評価と管理を計画し実施する。
教訓と事後検証プロジェクトに関連する知識を獲得するために、納入後評価またはプロジェクト後レビューを開催する。たとえば、見積もりモデル、教訓データベース、ゲートレビューのチェックリストなどを拡充・改善するためである。

Additional good practices can be found in INCOSE (2010, Clause 6.2), SEG-ITS (2009, Sections 3.9.3 and 3.9.10), INCOSE (2010, Section 5.2.1.5), and NASA (2007, Section 6.7).

その他の優れた実践は、INCOSE(2010, Clause 6.2)、SEG-ITS(2009, Sections 3.9.3 and 3.9.10)、INCOSE(2010, Section 5.2.1.5)、および NASA(2007, Section 6.7)に示されている。

References

参考文献

Works Cited

引用文献

Caltrans and USDOT. 2005. Systems Engineering Guidebook for Intelligent Transportation Systems (ITS), version 1.1. Sacramento, CA, USA: California Department of Transportation (Caltrans) Division of Research & Innovation/U.S. Department of Transportation (USDOT), SEG for ITS 1.1.

DAU. 2010. Defense Acquisition Guidebook (DAG). Ft. Belvoir, VA, USA: Defense Acquisition University (DAU)/U.S. Department of Defense (DoD). February 19, 2010.

INCOSE. 2012. Systems Engineering Handbook: A Guide for System Life Cycle Processes and Activities. Version 3.2.2. San Diego, CA, USA: International Council on Systems Engineering (INCOSE), INCOSE-TP-2003-002-03.2.2.

NASA. 2007. Systems Engineering Handbook. Washington, DC, USA: National Aeronautics and Space Administration (NASA), December 2007. NASA/SP-2007-6105.

SEI. 2007. "Measurement and Analysis Process Area," in Capability Maturity Model Integrated (CMMI) for Development, version 1.2. Pittsburgh, PA, USA: Software Engineering Institute (SEI)/Carnegie Mellon University (CMU).

Primary References

主要参考文献

Caltrans and USDOT. 2005. [[Systems Engineering Guidebook for Intelligent Transportation Systems (ITS)],] version 1.1. Sacramento, CA, USA: California Department of Transportation (Caltrans) Division of Research & Innovation/U.S. Department of Transportation (USDOT), SEG for ITS 1.1.

Caltrans and USDOT. 2005. Systems Engineering Guidebook for Intelligent Transportation Systems (ITS), version 1.1. Sacramento, CA, USA: California Department of Transportation (Caltrans) Division of Research & Innovation/U.S. Department of Transportation (USDOT), SEG for ITS 1.1.

DAU. 2010. Defense Acquisition Guidebook (DAG). Ft. Belvoir, VA, USA: Defense Acquisition University (DAU)/U.S. Department of Defense (DoD). February 19, 2010.

INCOSE. 2012. Systems Engineering Handbook: A Guide for System Life Cycle Processes and Activities. Version 3.2.2. San Diego, CA, USA: International Council on Systems Engineering (INCOSE), INCOSE-TP-2003-002-03.2.2.

NASA. 2007. Systems Engineering Handbook. Washington, DC, USA: National Aeronautics and Space Administration (NASA), December 2007. NASA/SP-2007-6105.

SEI. 2007. "Measurement and Analysis Process Area," in Capability Maturity Model Integrated (CMMI) for Development, version 1.2. Pittsburgh, PA, USA: Software Engineering Institute (SEI)/Carnegie Mellon University (CMU).

Additional References

追加参考文献

ISO/IEC/IEEE. 2009. ISO/IEC/IEEE 16326|Systems and Software Engineering - Life Cycle Processes - Project Management. Geneva, Switzerland: International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC)/Institute of Electrical and Electronics Engineers (IEEE), ISO/IEC/IEEE 16326:2009(E).